Quibal v. Sandiganbayan | 244 scra 224
Facts:
This is a petition for review of a decision of the Sandiganbayan. In convicting
the petitioner of violation of Sec. 3(e) of RA 3019 (Anti-graft and corrupt practices
Act). The municipality of Palapag Northern Samar, by its OIC Vice-mayor Teodoro
Bello entered into a contract with the Flores Construction Company, represented
by Eduardo Guevarra, for construction of the municipal public market. The
period of completion of the project was 100 days. The price was P652,562.60.
The petitioner issued (4) PNB checks in favor of the contractor in total amount
of P650,000.00. However, sometime in June 1988, after receipt of said payments,
the contractor abandoned the project. The COA special Audit Team inspected the
progress of the construction of the Palapag Municipal Market. It discovered
several irregularities. It found out that only about 36.24% of the construction
of the municipal market has been completed despite the lapse of the contract
period of 100 days. The actual cost of the finished work on the project was
only p301,745.65. Unfinished work, as evaluated, cost, P348,235.35. It was also
established that the contractor had non-completion of the building. Provincial
Auditor submitted an inspection report to the COA Regional Director
recommending appropriate legal action be taken against the petitioner. The
Ombudsman informed the Mayor of the charges filed against him by COA. After
trial, the Sandiganbayan promulgated decision convicting petitioner of the
crime charged.
Issue:
WON the required proof for violation of Section 3(e) of RA 3019 was complied.
Holding:
Yes. The required proof was: 1) the accused is a public officer discharging
administrative or official function or private persons charged in conspiracy
with them; 2) the public officer committed the prohibited and during the
performance of his official duty or in relation to his public position; 3) the
public officer acted with manifest partiality, evident bad faith or gross
inexcusable negligence; and 4) hid action caused undue injury to the Government
or any private party or gave any party any unwarranted benefit, advantage or
preference to such parties. The construction of the municipal market should
have been finished after the agreed period which is 100 days (March 7, 1988).
However, at the time of the Audit (Aug. 1988), only 36.24% of the construction
has been completed. Yet, out of the contract price of P652,562.60, petitioner
already paid the contactor a total of P650,000.00. In so doing, petitioner
disregarded the provision in the contract that payment should be based on the
percentage of work accomplishment. Moreover, the contract provided that in case
of delay in the completion of the project, the contractor shall be liable for
liquidated damages at the rate of 1/10 or 1% of the contract price per day of
delay. By their acts, petitioner clearly acted with manifest partiality and
evident bad faith relative to the construction of the municipal market. Petitioner
acts and omissions demonstrated an utter lack of care in enforcing the contract
of the construction. It cannot be successfully argued that the acts and
omissions of petitioner did not cause damage or injury to the municipal
government, because the construction was completed only at the end of December
1989 when it should have been finished by March 1988. This unnecessary delay of
almost 2 years cause considerable monetary loss to the municipal government in
the form of monthly rentals.
Comments
Post a Comment